When an elevated section is optional, ask for three comparable prices: the base circuit, the bridge supply, and the changes the bridge creates elsewhere in the project. This makes it possible to compare a flat concept with an elevated one using quantities taken from each drawing.
What does a karting bridge cost to supply?
On 28 November 2026 the public MRK estimator displayed €2,500 per linear metre, excluding VAT, for the 5 m wide bridge configuration, with a 60 m minimum when selected. The public line includes the bridge, deck and guardrails. MRK should confirm the price for other widths and confirm the detailed scope for any specific project. View the MRK supply estimator.
| Option | Bridge supply calculation | Bridge supply |
|---|---|---|
| A · 60 m bridge | 60 × €2,500 | €150,000 |
| B · 80 m bridge | 80 × €2,500 | €200,000 |
In this example, B adds €50,000 of bridge supply. If the public simulator’s optional calculation note is included at its displayed 1.5% of bridge value, that adds €2,250 in A or €3,000 in B. With that line selected in both examples, the difference is €50,750 for those two items. These are calculations from the public tariff. Project requirements and the Studio’s own pricing may vary.
Compare added and removed quantities on the full circuit
Take the two marked-up layouts and ask for a line-by-line difference. An elevated section may replace some ground-level barriers and add treatment to the upper deck. Confirm which guardrails are included in the bridge and which barrier runs need their own line. Count only the resin areas included in the selected scope, including the deck if specified.
Keep a separate line for the two track lengths. If the project objective is a longer lap, show the extra metres of lap and the change in the quoted scope beside one another. The bridge length counts the structure, while the lap length counts the route. Subtracting the flat-track total from the elevated-track total is meaningful once both offers include the same design stage and installation scope.
Use the main track cost guide for the comparison method, and see three MRK Track Studio estimates to see which lines can change between concepts.
Ask who prices installation and interfaces with the building
Get separate items for transport, unloading, lifting and installation, preparation of supports, any application of resin and applicable taxes. Ask whether access for delivery or assembly changes between options. Agree the engineering scope and who checks the existing building, how the ramps are arranged and which drawings are required to confirm the layout.
Record each owner and mark each line as included, excluded or pending. For a usable comparison, keep pending items visible and agree a date for pricing them before choosing the option.
Request a baseline and an elevated alternative
Send MRK your building plan, known heights, the common layout brief and the reason you are considering a bridge. Ask for a baseline estimate and an elevated alternative itemised on the same basis. Explore MRK multi-level track structures and track design and construction, then request an itemised quotation.