When a circuit is handed over, can the duty manager identify the exact spare part for a damaged section without calling the installer who built it? Set up a spare parts register while the supplier, installation team and operator can still check the references together. The register should let the operator go from a location on the circuit to a confirmed part, find usable stock and prepare a reorder.
Link each spare to the installed equipment
Start with the as-built plan and the supplier’s parts list. Give each serviceable location an identifier that makes sense to the team, such as a track sector, level and side. Keep the location code and the supplier’s item reference in separate fields. The same item may serve several locations, and one location may contain several part variants.
For example, a log entry might say “R1, bend 4, inside”, with a photograph of the fitted assembly and a link to the supplier’s drawing revision. Add the model or variant where it affects compatibility. On MRK’s karting barrier system, the polyethylene band, spring-supported posts and connections are part of an assembly. Ask the supplier which parts or kits can be ordered separately and how to tell approved variants apart. Apply the same method to other equipment covered in the handover pack.
Build a register the duty team can use
Use one stock line per confirmed reference and link it to every relevant location. Record optional alternatives only after the supplier or responsible specialist has confirmed where they can be used. The following fields work in a shared spreadsheet or maintenance system.
- Identification. Part name, supplier reference, variant, drawing or manual revision and mapped locations.
- Stock status. Quantity received, quantity available for use, quantity allocated to work, and stock with a condition or compatibility check pending.
- Storage. Labelled bin or shelf, packaging identifier, handling or storage instructions, and batch or expiry where applicable.
- Reorder information. Confirmed supplier contact, order unit, latest quoted lead time and its date, and the person responsible for purchase approval.
Record open handover defects separately. If a part is needed to finish installation or clear a defect, allocate it to that work before counting the opening reserve. Keep damaged, unidentified or unconfirmed stock out of the available balance until it has been assessed.
Decide what to keep on site
Discuss each part in terms of the impact of a shortage, the number of fitted locations it can serve, confirmed supplier lead time and storage constraints. A common item approved for several sectors may warrant a different stocking decision from a custom part that fits only one ramp. Have the supplier confirm the available variants and the order quantities, then revise the stock policy using actual usage and delivery records after opening.
Ask for separate quote lines for the installed equipment and the opening spares. Specify whether transport, unloading and installation are included or quoted separately. If the offer includes resin work, separate material supply, substrate preparation and application. Compare both the net amount and the applicable VAT or other taxes as confirmed in the offer. MRK’s track supply simulator estimates the listed equipment quantities. Request a separate quotation for spare parts and confirm their references.
Test the register before acceptance
Pick a sector and run a short desk exercise with the duty team. Give them a location and a photograph. Ask them to identify the fitted variant, locate the correct stock record and bin, and draft a reorder request. For any unidentified item, record who will confirm the reference and by when. Repeat the exercise on another level or sector if the project uses different hardware there.
When a part leaves stock, record the date, quantity and work reference. Confirm who can authorise the intervention and who signs off return to service under the site’s procedures. The MRK guide to manufacturing quality helps specify the original documentation. The karting centre operations guide puts the register into the team’s day-to-day handover and maintenance routines.